| Tech. Q. Master Brew. Assoc. Am., Oct/Nov/Dec. 1972, 9(4), 215-217. English
|
|
The planning and start-up of a high speed bottling line.
|
|
Pugh, A.G. and Fortier, F.G.
|
|
|
|
Abstract
What is considered to be good practice in planning for a start up and the actual start up of a fast bottling line is described. Conveyor systems caused the greatest start up problems, particularly with bottle handling on the conveyors. The bottling efficiency attained 87% after 48 days of operation with filler speeds of 1200 bottles per min.
Keywords: bottling conveyor efficiency planning
|
| |
|